Compute the IRR static for Project E. The appropriate cost of capital is 7 percent.(Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project E
Time: 0 1 2 3 4 5
Cash flow -$1,700 $630 $690 $660 $440 $240
IRR______ %
Should the project be accepted or rejected?