a(4). Find the
critical path
and the project
completion time.
b(7). Make a table
of ES, EF, LS, and LF for each activity.
c(2).
How much slack is there in
activity B.
d(7).
The entrepreneur is considering
reducing the time for completion of
the project. He can hire an additional worker to help reduce the
times only for activities C, D, F, and G. In each case the worker
can reduce the time required by one day for $100 each.
Please provide complete logic
for your answer.
(i) Which
activity should the worker perform to
reduce the project completion time by one
day?
(ii) Which activities should
the worker perform to reduce the project completion time by two
days?
Show transcribed image text yec End Start a. Find the critical path and the project comple- tion time. b. What are the ES, LS, EF, and LF for each activity?
yec End Start a. Find the critical path and the project comple- tion time. b. What are the ES, LS, EF, and LF for each activity?