Activity Activity Predecessor
Time (weeks)
A …… 5
B A 8
C A 3
D B 7
E C 6
F D, E 10
16) Using Table A above, the latest start (LS) for
activity B is
a) 5
b) 8
c) 13
d) 14
17) Using Table A above, the critical path for this
project consists of activities
a) A-B-C-D-E-F
b) A-C-E-F
c) A-B-C-F
d) A-B-D-F