Analyze case study at:
http://scaledagileframework.com/john-deere-case-study-part-2/
Analyze the case study
at: http://www.infoq.com/news/2006/11/scrum-9-months-later
Assignment
Write up your analysis of the two case studies. Refer to
specific issues in the case in your analysis.
case1 john deere case reaching the tapping points
case 2
Casestudy: Effects of Scrum, 9 months later
by Floyd Marinescu on Nov 07, 2006 | Discuss
Share

|
Read later
My Reading List
Richard Banks wrote back in February about his failed attempt to
successfully introduce Scruminto his organization, concluding that
“if you are planning on implementing Scrum you need to do it treat
it as an all-or-nothing change.” Richard had introduced parts of
Scrum but didn’t follow the rules. He “allowed ad-hoc requests to
be actioned, allowed staff to be pulled off for other non
development work and as a result failed to get the team to own the
process and to own the delivery of results.” He also held the roles
of ProductOwner and ScrumMaster which “led to conflicts of interest
over what was best for the company over what was best for the
team.”
Since then Richard started from scratch and tried to implement it
properly. 9 months later, Richard reports that Scrum is “not only
well implemented in product development but the principles of scrum
are starting to filter through to other areas of the business.”
Richard’s blog summarizes the key areas that he’s noticed Scrum
cause positive change in his organization, summarized here:
More Ownership. The team implements quality
from the beginning and has developed a culture of teamwork and
responsibility.
Less Centralised Management. The team is
self-organizing; they do their own estimates and task allocation
and rarely escalate problems that could be solved internally.
More Planning. Stake holders and product owners
are more involved in the dev process, more thought being put into
the priority and order of tasks. Less scope creep/ad-hoc requests
are occuring because of strict rules about cancelling the sprint if
resources are re-assigned, making requestors more careful or risk
negatively impacting the business in very clear ways.
Less Staff Turnover. Working at a sustainable
pace, feeling ownership over their work, having clear achievable
goals has dramatically cut turnover. According to Richard “Even if
Scrum didn’t bring all the changes listed here then this alone
would have made it worthwhile.”
More Customer Focus. Customers are more
invovled in planning, prioritization, feedback, useability testing,
etc. The risk of producing software the client doesn’t need is
reduced.
A Better Product. “The things we have added to
the product are what customers are asking for and so our value
proposition for the customer is improved.”
Organisational Change. The company morale and
teamwork are improved, as is the ability for the organization
deliver value to their customers.