Show transcribed image text Consider the office renovation project data in the table below. A "zero" time estimate means that that the activity could take a very small amount of time and should be treated as a numeric, zero in the analysis. Use two decimals when you calculate the expected time and variance of activities. Find the critical(you may want to use OM Solver for this question). Based on the critical path, find the probability of completing the office renovation project by 39 days. Find the date by which you would be 90 percent sure of completing the project.
Consider the office renovation project data in the table below. A "zero" time estimate means that that the activity could take a very small amount of time and should be treated as a numeric, zero in the analysis. Use two decimals when you calculate the expected time and variance of activities. Find the critical(you may want to use OM Solver for this question). Based on the critical path, find the probability of completing the office renovation project by 39 days. Find the date by which you would be 90 percent sure of completing the project.