Problem 13-21
Consider the following project network and activity times (in
days):
The crashing data for this project are as follows:
Identify the critical activities and find the expected project
completion time.
| Activity | Critical |
|---|---|
| A | Yes |
| B | No |
| C | Yes |
| D | No |
| E | Yes |
| F | No |
| G | No |
Project Completion Time = days
What is the total project cost using the normal times?
$