Q 7:
Project development software is 7 days behind at day 60. Its
planned cost are $830 for this point in time. The actual cost is
$645. Estimate variances to give your answer as to the health of
the project. If the actual cost had been $745, re-estimate the
variance and give you answer to the health of the project.
|
AC = $645 |
AC = $745 |
|||||||
|
Day |
AC |
PV |
EV |
Day |
AC |
PV |
EV |
|
|
CV |
CV |
|||||||
|
CPI |
CPI |
|||||||
|
SV |
SV |
|||||||
|
SPI |
SPI |
|||||||
|
CSI |
CSI |
|||||||
|
TV |
TV |
|||||||