The following table provides the information necessary to
construct a project network and project crash data
(a) Construct the project network
(b) Determine the maximum possible crash time for the network,
and crash the network the maximum amount possible
(c)Compute the normal project cost and the cost of the crashed
project. Please provide detail answers.
Activity Activity
Predecessor Normal time
(weeks) Crash time
(weeks) Normal
Cost Crash Cost
1
–
20
8
1000
1480
2 – 24
20
1200
1400
3 –
14
7
700
1190
4
1
10
6
500
820
5
3
11
5
550 730