Week |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
Quantity Needed |
0 |
0 |
0 |
45 |
65 |
75 |
90 |
85 |
Determine the timing of
the Planned Receipts and Planned Order Releases for the leg
assemblies assuming Scheduled receipts of 35 units in week 1 and a
Projected On-hand Inventory on 40 units. Assume an Economic Order
Quantity lot sizing rule where the EOQ is 100.
|
Item: Leg Assembly Lot Description: Lead Time: 2 |
||||||||
|
Week |
||||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
|
Gross Requirements |
||||||||
|
Scheduled Receipts |
||||||||
|
Projected Available |
||||||||
|
Net Requirements |
||||||||
|
Planned Receipts |
||||||||
|
Planned Order Releases |
|